RFQ rounds allow procurement teams to review supplier quotations until they have valid, comparable proposals. Each round needs a purpose: clarifying an exclusion, completing missing information, updating requirements or requesting revised pricing on a consistent basis.
Receiving the initial quotations does not mean that the request for quotation is complete. One supplier may exclude transport, another may interpret the scope differently, and a third may leave the delivery date unconfirmed. Before negotiating, Procurement needs to resolve these differences and retain the context behind each revision.
What are RFQ rounds?
An RFQ round is a further stage of requesting and receiving responses within the same purchasing process. It allows buyers to ask suppliers to clarify, complete or revise their proposals, with defined instructions and a deadline.
For an overview of the full process, read our guide to what an RFQ is and how it works. Here, we focus on what happens after the initial quotations arrive.
Opening another round should address a specific need. Asking for successive price reductions without resolving the scope can produce different prices that are still not comparable.
When should you open a new round?
- Information is missing: required fields, documents or confirmations have not been provided.
- There are exclusions: one proposal leaves out activities or costs included in others.
- Technical differences remain: the team needs to clarify whether an alternative meets the requirements.
- Specifications change: quantities, deliveries or project conditions are revised.
- Revised pricing is required: proposals are already aligned and suppliers are asked to update prices under the established conditions.
A specific clarification may be resolved through a documented query. If the basis on which participants must respond changes, communicate the revision to everyone affected and set an appropriate new deadline.
How to organise RFQ rounds step by step
1. Review the initial quotations
Check technical compliance, quantities, units, included costs and commercial terms. Distinguish missing information from confirmed non-compliance: an incomplete response needs clarification before conclusions are drawn.
You can use the criteria in our guide to comparing supplier quotations to support this review.
2. Define what the next round must resolve
Prepare a specific list of questions and changes. Explain what each supplier must correct, which documents they must provide and which conditions remain unchanged. Avoid vague requests such as “improve your quotation” when the issue is an excluded installation service or a misunderstood quantity.
3. Communicate a consistent basis
Identify the current version of the specifications and explain what has changed. Affected suppliers need the information required to respond on comparable terms, while the confidentiality of competing proposals must be respected.
4. Assign responsibilities and set a deadline
Define who answers queries, who validates technical matters and when revised proposals are due. Allow enough time to assess the changes: revising the scope may require more work than confirming an administrative detail.
5. Retain versions and review responses
Associate each quotation with its supplier, round and date. Keep the previous proposal together with the clarifications that explain the new version. Then check which issues have been resolved and which remain open.
This traceability helps explain changes in the assessment and prevents an old price from being used with new conditions by mistake.
An example of a review across several rounds
The following example is illustrative. A company requests quotations for industrial equipment, including transport, installation and commissioning.
| Stage | Situation | Procurement action |
|---|---|---|
| First round | One supplier excludes installation and another does not confirm commissioning. | Record the differences and request responses covering the same scope. |
| Second round | Suppliers complete the scope, but a delivery lead-time exception remains. | Check with the requester whether the lead time is acceptable and ask for confirmation. |
| Closing the review | Acceptable proposals are complete and their terms are identified. | Prepare the evaluation and decide the next negotiation step. |
There is no universal number of rounds. If every revision introduces new requirements, the purchase may need to be redefined before further quotations are requested.
When to close the rounds and move to negotiation
The review can close when the team has enough information to evaluate the proposals and understands which exceptions it has accepted or rejected. Before moving on, check that:
- Technical requirements and scope are confirmed.
- Prices relate to comparable quantities, units and conditions.
- Exclusions and additional costs have been resolved or identified for evaluation.
- Each supplier’s current quotation and validity period are known.
- Relevant clarifications and decisions are recorded.
If the next stage is an electronic auction, also review what to check before preparing the auction. Receiving several quotations is not enough to confirm that all participants are ready to compete.
Common mistakes to avoid
Mixing versions. Comparing the price from one round with the scope from another can distort the assessment. Always identify the proposal being used.
Changing requirements without explaining the impact. If a specification changes, make clear whether a new technical proposal, commercial quotation or both are required.
Adding rounds without a purpose. Each review takes time for the team and suppliers. Define what needs to be resolved before the stage can close.
Confusing the best quotation with the contract award. The decision should consider the established requirements and criteria, together with the relevant validations and approvals.
Managing RFQ rounds with APTSE
APTSE’s RFQ software supports different rounds within the same process: requesting clarifications, completing proposals, incorporating changes and asking for revised pricing while maintaining traceability between versions.
Centralising this information helps the team work with the context of the negotiation. Technical validation and the purchasing decision still require the judgement of the people responsible.
To organise supplier requests, responses and revisions, contact APTSE and request a demonstration.